The crippled Fukushima Dai-ichi nuclear power station is seen through a bus window in Okuma on November 12, 2011.
Nuclear crisis minister Goshi Hosono suggested that the timetable was ambitious, acknowledging that decommissioning three reactors with severely melted fuel plus spent fuel rods at the Fukushima Dai-ichi plant was an "unprecedented project," and that the process was not "totally foreseeable."
"But we must do it even though we may face difficulties along the way," Hosono told a news conference.
Under a detailed roadmap approved earlier Wednesday following consultation with experts and nuclear regulators, plant operator Tokyo Electric Power Co. will start removing spent fuel rods within two to three years from their pools located on the top floor of each of their reactor buildings.